IRS Notice 2026-11, released in January 2026, tells taxpayers how the 100 percent bonus depreciation rules in the One Big Beautiful Bill Act apply: rely on the existing bonus depreciation regulations, with the old 2017 dates replaced by January 19, 2025. The catch is in the date. To get the full 100 percent, the property must be both acquired and placed in service after January 19, 2025, and under the written binding contract rule your acquisition date is the date your contract became binding, not the date you closed. An owner who signed in early January 2025 and closed in March may be on the 40 percent side of the line without knowing it. For a building under construction across the line, the component election the notice preserved can save the pieces that were built after the cutoff.
Denise signed a contract on January 9, 2025 to buy a 30,000 square foot flex building on the north side of Huntsville, Alabama, for $1.6 million. The deal closed on March 14, 2025. In September her accountant started the cost segregation planning and stopped at the first question on his checklist.
"When did you sign the contract? Not when you closed. When you signed."
Denise did not see why it mattered. She closed in March, two months after the January 19 cutoff for the restored 100 percent bonus. The closing date was on the right side. She assumed the property was too.
It might not be. The statute and the regulations say property is not treated as acquired after the date you entered into a written binding contract for it. If Denise's January 9 contract was binding on January 9, her acquisition date was January 9, and her property falls under the old phase-down at 40 percent. The study was expected to reclassify about $400,000 of components. The arithmetic below shows what the two rates do to her 2025 return, and the whole swing turns on the day she signed.
These figures are illustrative. The appraisal put $320,000 on land, leaving $1,280,000 of depreciable basis. The building is nonresidential, 39-year property, placed in service in March 2025, so the first-year rate on the building is the IRS mid-month table rate for March, 2.033 percent. The engineering supported $400,000 of the basis as shorter-life property, 31 percent: $250,000 examined as 5-year property (dedicated electrical and compressed-air runs serving tenant equipment, removable flooring and demountable office partitions) and $150,000 as 15-year land improvements (the truck court paving, fencing, site lighting and landscaping). The remaining $880,000 stays on the 39-year schedule.
| 2025, first year | Acquired after January 19, 2025 (100 percent) | Acquired on or before January 19, 2025 (40 percent) |
|---|---|---|
| Bonus on $400,000 of reclassified property | $400,000 | $160,000 |
| Regular first-year depreciation on the rest of the reclassified property (half-year convention) | $0 | about $34,500 |
| 39-year building, $880,000 at 2.033 percent | $17,890 | $17,890 |
| Total first-year deduction | $417,890 | about $212,400 |
The gap is about $205,500 of deduction in 2025, which at a 37 percent federal rate is about $76,000 of federal tax moved into later years. Denise qualifies as a real estate professional, materially participates in the building, and files jointly, so the loss is nonpassive and sits under the Section 461(l) cap of $626,000 for 2025, adjusted annually. Every dollar of that $76,000 is still deductible over time on the 40 percent side. What changes is the year it arrives.
The One Big Beautiful Bill Act, signed July 4, 2025, made 100 percent bonus depreciation permanent for qualified property acquired and placed in service after January 19, 2025. Property acquired on or before that date stays under the phase-down that was already in the law: 40 percent for property placed in service in 2025, 20 percent in 2026.
That left one question for every owner who bought or built near the line: how do I know which side I am on? Notice 2026-11 answered it by choosing continuity. Instead of writing new rules, the IRS told taxpayers they may rely on the existing bonus depreciation regulations under Reg. 1.168(k)-2, the ones written for the 2017 Tax Cuts and Jobs Act cutoff, with the September 27, 2017 dates replaced by January 19, 2025. The machinery practitioners already know for acquisition dates, binding contracts, self-constructed property and the component election carries forward. Taxpayers can rely on the notice now, while formal regulations are written.
Three pieces of that machinery matter to a building owner.
The 100 percent rate requires that the property be acquired after January 19, 2025 and placed in service after January 19, 2025. Most owners track only the placed-in-service date, the day the building was ready and available for use, because that is the one that feels like the start. The acquisition date is the one that catches people, because it is often earlier than the closing.
For purchased property, the regulations treat the property as acquired on the date the taxpayer entered into a written binding contract to acquire it. A contract is binding if it is enforceable under state law against the buyer and does not limit the buyer's damages to a specified amount; a provision that limits damages to at least 5 percent of the contract price is not treated as a limit. A contract is still binding if it is subject to a condition, as long as the condition is not within the control of either party.
That last sentence is where Denise's accountant went to work. Many purchase contracts give the buyer a free-look period during which the buyer can walk away for any reason and get the deposit back. During that period the contract is conditioned on something entirely within the buyer's control. The date the contract became binding may be the day the inspection period expired and the deposit went hard, whatever date is next to the signatures. If Denise's free-look ran through January 24, 2025, her accountant has a documented argument that the contract became binding after the cutoff. If the deposit went hard on January 9, she is on the 40 percent side.
That analysis belongs with your CPA, with the contract in hand, and it has to happen before you file.
For property you build rather than buy, the acquisition date is the date physical work of a significant nature begins, and the regulations offer a safe harbor: work is significant once more than 10 percent of the total cost has been incurred. A building whose foundation was poured in December 2024 was acquired before the cutoff, no matter when it was finished.
The notice preserved the component election under Reg. 1.168(k)-2(c). For a larger self-constructed property whose construction began before the cutoff, the taxpayer may elect to treat components acquired or built after the cutoff as eligible for the 100 percent rate on their own. The steel erected in November 2024 stays at 40 percent. The electrical, the finishes, the site work and the equipment installed in April 2025 can come through at 100 percent, if the election is made and the components are documented.
The election is only as good as the component analysis under it. That is engineering work: which components, what they cost, and when each was acquired or built, tied to the pay applications.
A percentage estimate cannot support a component election, because it has no components. A fully engineered and accounted cost segregation study works component by component under the first two approaches the IRS Audit Techniques Guide describes: Approach 1, detailed engineering from actual cost records, and Approach 2, engineering with documented estimates reconciled to actual cost. On a project that straddles the cutoff, the schedule carries each component's cost, its recovery period and its acquisition date, so your CPA can apply the right bonus rate to each line and an examiner can trace it. The study is signed by credentialed professionals, and Cost Seg America defends it for as long as you own the building, no time limit, no hour cap, no additional fee, with written responses and participation in examiner calls alongside your CPA.
Treating the closing date as the acquisition date. The binding contract date controls, and it can fall before the cutoff while the closing falls after.
Tracking only the placed-in-service date. Both dates must clear January 19, 2025 for the full rate.
Deciding the binding contract question yourself. Whether a free-look period, a financing contingency or a damages clause changes the binding date is a legal question with a documented answer. Guessing it on a return is how a $76,000 swing becomes an examination question.
Ignoring the component election on a straddling project. A building started in late 2024 and finished in 2025 can still get 100 percent on the parts built after the cutoff, but only with the election and the engineering to support it.
Assuming the 40 percent side means no study. The phase-down rate still front-loads 40 percent of the reclassified property into year one, and the shorter recovery periods apply to the rest. The study usually still pays.
If you signed, closed and placed the property in service all after January 19, 2025, the date question is settled and the full rate applies. Most owners buying in late 2025 and 2026 are in this group.
If you placed the property in service before January 20, 2025, you are under the prior rules regardless of contract date, and the catch-up through Form 3115 uses the bonus rate of that year.
If the property has under $180,000 of depreciable basis after land, or you plan to sell within a year or two, the study itself may not pencil out on either side of the line, and the date question is moot.
Interim guidance released in January 2026 on how the One Big Beautiful Bill Act's 100 percent bonus depreciation applies. It lets taxpayers rely on the existing bonus depreciation regulations with the cutoff dates updated to January 19, 2025.
Because the 100 percent rate requires the property to be acquired and placed in service after January 19, 2025, and for purchased property the acquisition date is the date the written contract became binding, which can be before the closing.
It is enforceable under state law against the buyer, does not cap the buyer's damages below 5 percent of the price, and any conditions are outside the control of the parties. A free-look period the buyer controls can delay the binding date until it expires.
If the December contract was binding when signed, the property was acquired before the cutoff and gets 40 percent for 2025. Your CPA should read the contract for a contingency that pushed the binding date past January 19.
The acquisition date is when physical work of a significant nature began, with a 10 percent of cost safe harbor. If that was before January 20, 2025, the component election can still bring components built after the cutoff through at 100 percent.
No. The election applies to larger self-constructed property. A purchased building is acquired on its binding contract date as a whole.
No. The new 100 percent deduction for qualified production property under Section 168(n) is a separate provision awaiting its own guidance.
Usually. Forty percent of the reclassified property still comes out in year one, and the rest comes out over 5, 7 and 15 years instead of 27.5 or 39. The free proposal will show the number under your rate.
If you signed a contract or started construction anywhere near January 19, 2025, pull the contract before your filing date and find the date the deposit went hard or the date the first significant work began. Then send Jim Dougherty and his team the property address, the purchase price, the contract date and the closing date. You will get a free proposal within 24 hours showing the estimated first-year deduction at your rate, the method, the timeline and the fee. Studies are delivered in 30 days, with rush available. Call 1-888-365-5023 or email info@costsegamerica.com.
This article is educational and is not tax advice for your situation; confirm the treatment with your CPA before filing.
Use the calculator, see your number, and request your free, no-cost proposal - delivered in 24 hours, with your flat fee quoted upfront and no obligation.